Condo handover inspection: 12 things to check before transfer
Published 2026-11-02 · by the NestThai team
Handover inspection day is when the buyer has the most leverage, because the final payment has not yet been made. Any defects must be fixed by the developer first. Schedule the inspection in daytime with plenty of natural light, and bring the right tools.
What to bring
- Torch, spirit level and tape measure
- A socket tester or phone charger
- Coloured tape to mark defects
- A small bucket of water to test drainage
12 points to inspect
- Walls and ceilings – cracks, damp stains, uneven paint
- Floors – lifted tiles, hollow sounds when tapped, incomplete grout
- Doors and windows – open and close smoothly, lock properly, seals intact
- Balcony – slopes toward the drain, no standing water
- Bathroom – toilet, shower, drains, no sewer smell
- Sockets and switches – test every one, including earthing
- Breaker panel – circuits clearly labelled and working
- Air conditioning – run for 15 minutes and check for drips
- Plumbing – water pressure, leaks under the sink
- Built-in furniture – hinges, drawers, edges and corners
- Intercom and key cards – all working
- Water and electricity meters – note starting readings and photograph them
When you find a defect, photograph it with its location and ask for an inspection record signed by the developer’s staff. Then book a re-inspection after repairs, before the ownership transfer date.